POWERGRID Khetri Transmission System Limited
Acq Date :
Date of Incorporation :
Financial Statements -
Director List
Commissioned
TBCB Subsidiaries
Annual Report - PKTSL_AR.pdf (3.54 MB)
PKTLFS.PDF (14.83 MB)
1) Establishment of 765/400kV, 2x1500 MVA S/s at suitable location near Khetri with 765kV (2x240MVAR) and 400kV (1x125 MVAR) bus reactor
- 765/400kV- 2x1500MVA
- 765kV ICT bay-2
- 400kV ICT bay-2
- 400kV line bay-2
- 765kV line bay-2
- 240 MVAr (765kV) Bus Reactor -2
- 125MVAr (400 kV) Bus Reactor -1
- 765 kV Reactor bay – 2
- 400 kV Reactor bay -1
- 1X500 MVA, 765/ 400 kV, 1-ph ICT (spare unit)
- 1X80 MVAR, 765 kV, 1-ph Reactor (spare unit)
(for both 1X240 MVAR bus reactor and 2X240 MVAR line reactor on Bikaner – Khetri 765kV D/c line at Khetri end)
Future provisions:
Space for:
- 765/ 400 kV ICTs along with bays: 2 nos.
- 400/220 kV ICTs along with bays: 4 nos.
- 765kV line bays: 4nos
- 400kV line bays: 4nos.
- 220kV line bays: 7nos
2) Khetri – Sikar (PG) 400kV D/c line (AL59)
3) 400kV line bays at Sikar (PG) for Khetri – Sikar (PG) 400kV D/c line (Twin AL59)
4) Khetri– Jhatikara 765kV D/c line
5) 765kV bays at Jhatikara for Khetri– Jhatikara 765kV D/c line
6) 1x240 MVAR Switchable Line reactors for each circuit at Jhatikara end of Khetri – Jhatikara 765kV D/c line along with reactor bays
- 1X80 MVAR, 765 kV, 1-ph Reactor (spare unit)
(for 240 MVAR line reactor on each ckt of Khetri – Jhatikara 765 kV D/c line at Jhatikara end)