Skip to main content
Loading

Press Releases

POWERGRID fully commissions 
India's First VSC based HVDC system

Source
Corporate Communications

POWERGRID has commissioned the 765 kV Wardha – Nizamabad D/C line along with the 765 / 400 kV Nizamabad GIS Substation well ahead of scheduled completion time of May, 2018 this system will facilitate import of power from Western Region mainly Chattisgarh for which Long Term Access has been granted to Telangana.  As per the desire of Hon’ble Chief Minister of Telangana, the Project was fast tracked and completed in a record time and fulfilled the commitment given to the state.  Power Grid wishes to place on record the excellent support rendered by the State and various districts administration to complete this project.

During this Financial year only POWERGRID completed another major inter-regional link by commissioning the corridor of 765kV Angul – Srikakulam – Vemagiri D/C line facilitating the import of Eastern Region power into Southern Region in Jan.2017. 

With the commissioning of the above two links, an inter-regional power transfer capacity of 9000 MW is made available to the entire Southern Region.  Apart from the above, a 400 / 220 kV Substation to evacuate power from Solar Park at N.P.Kunta was commissioned in a record period of 7 months from handing over of land in this year.  This has greatly boosted the renewable energy integration into the grid. 

In the coming year 2017-2018 POWERGRID through its Subsidiary PSITSL, is implementing the Transmission System BeyondVemagiri which enables power transfer to the new Capital region of Andhra Pradesh and further connection to Kadapa and Tumkur. 

The works of ±800 kV Raigarh – Pugulur HVDC Project will also be under implementation and the completion of which will enable further inter – regional power transfer capacity of 6000 MW for the Southern Region. 

Issued by: Corporate Communications

Follow us on Twitter: @pgcilindia