Skip to main content
Loading

Subsidiaries

POWERGRID KHAVDA II- B TRANSMISSION LIMITED

Transmission scheme for evacuation of 4.5GW RE injection at Khavda PS under Phase…

  • Acq Date : 21-03-2023
  • Date of Incorporation : 21-04-2022
  • Project Status : Under Implementation
Know More

POWERGRID ER NER Transmission Limited

Scope 1) Creation of 220kV GIS bus at Banka (POWERGRID) S/s 2) 400kV bus…

  • Acq Date : 10-10-2022
  • Date of Incorporation : 06-10-2021
  • Project Status : Under Implementation
Know More

POWERGRID Neemuch Transmission System Limited

Scope 1) Establishment of 2x500 MVA, 400/220 kV Pooling Station (AIS) at Neemuch…

  • Acq Date : 24-08-2022
  • Date of Incorporation : 12-04-2022
  • Project Status : Commissioned
Know More

POWERGRID Gomti Yamuna Transmission Limited

1) Construction of 400/220/132 kV GIS substation (2x500+2x200 MVA), Mohanlalganj (…

  • Acq Date : 30-05-2022
  • Date of Incorporation : 08-06-2021
  • Project Status : Commissioned
Know More

POWERGRID Narela Transmission Limited

1) Establishment of 765/400 kV, 3X1500 MVA GIS substation at Narela with 765 kV (…

  • Acq Date : 11-05-2022
  • Date of Incorporation : 15-05-2020
  • Project Status : Under Implementation
Know More

POWERGRID Vemagiri Transmission Limited

A) Vemagiri Pooling Station- Khammam 765kV D/C transmission line B) Khammam-…

  • Acq Date : 18-04-2022
  • Date of Incorporation : 21-04-2011
  • Project Status : Project Approval Withdrawn by CERC
Know More

POWERGRID Aligarh Sikar Transmission Limited

1) Sikar-II - Aligarh 765kV D/c line      Future provisions: Space for 400/220…

  • Acq Date : 08-06-2021
  • Date of Incorporation : 17-05-2020
  • Project Status : Under Implementation
Know More

POWERGRID Sikar Transmission Limited

1) Establishment of 765/400 kV, 2x1500 MVA at Sikar – II with 400kV (1x125 MVAR) and…

  • Acq Date : 04-06-2021
  • Date of Incorporation : 11-06-2020
  • Project Status : Under Implementation
Know More

POWERGRID Bhadla Transmission Limited

1x240 MVAr Switchable line reactor for each circuit at each end of Fatehgarh-II –…

  • Acq Date : 04-06-2021
  • Date of Incorporation : 02-06-2020
  • Project Status : Under Implementation
Know More

POWERGRID Bikaner Transmission System Limited

1) Establishment of 400 kV switching station at Bikaner –II PS with 420kV (2x125…

  • Acq Date : 25-03-2021
  • Date of Incorporation : 12-05-2020
  • Project Status : Commissioned
Know More

POWERGRID Himachal Transmission Limited

400 kV Quad Bundle Conductor Double Circuit Line from Karcham Wangtoo HEP Pothead…

  • Acq Date : 25-03-2021
  • Date of Incorporation : -
  • Project Status : Commissioned
Know More

POWERGRID Ramgarh Transmission Limited

A) Establishment of 400/220 kV, 4x500 MVA at Ramgarh – II (Fatehgarh-III) PS with…

  • Acq Date : 09-03-2021
  • Date of Incorporation : 26-06-2020
  • Project Status : Commissioned
Know More