POWERGRID Sikar Transmission Limited
Acq Date :
Date of Incorporation :
Financial Statements -
Director List
Under Implementation
TBCB Subsidiaries
Annual Report - PSTL.pdf (11.37 MB)
PSTL.pdf (7.01 MB)
Formerly known as Sikar New Transmission Limited
1) Establishment of 765/400 kV, 2x1500 MVA at Sikar – II with 400kV (1x125 MVAR) and 765 kV (2x330 MVAr) bus reactor
- 765/400 kV, 1500 MVA ICT – 2
- 765/400 kV, 500 MVA spare single-phase ICT-1
- 765 kV ICT bays – 2
- 400 kV ICT bays – 2
- 765 kV line bays –2
- 400 kV line bays- 2 125 MVAr, 420 kV bus reactor-1
- 420 kV reactor bay –1
- 330 MVAr, 765 kV bus reactor- 2 (6x110 MVAR)
- 765 kV reactor bay- 2
- 110 MVAR, 765 kV, 1 ph Reactor (spare unit) -1
(common spare unit for banks of Bus Reactor & Line Reactor)
Future Provision Space for
- 765/400kV ICT along with bays-2
- 765kV line bays along with switchable line reactors- 10
- 400kV line bays along with switchable line reactor- 6 400kV bus reactor- 2
2) Bhadla-II PS – Sikar-II 765kV D/c line 3) 2 no. of 765 kV line bays at Bhadla- II for Bhadla-II PS – Sikar-II 765kV D/c line
- 765 kV line bays –2
4) 1x330 MVAr switchable line reactor for each circuit at Sikar-II end of Bhadla-II PS – Sikar-II 765kV D/c line.
- 330MVAr, 765 kV reactor- 2
- Switching equipment for 765 kV reactor – 2
5) 1x240MVAr switchable line reactor for each circuit at Bhadla-II end of Bhadla-II PS – Sikar-II 765kV D/c line
- 240 MVAr, 765 kV reactor-2
- Switching equipment for 765 kV reactor – 2